USC Coliseum Renovations Top Off!

It’s a beautiful day for a celebration! Together with our partner AECOM-Hunt, we celebrated the project’s Topping Off with the USC community.

 

Structural steel is almost complete after 2,131 tons of steel and 1,740 tons of rebar have been used so far! MEP and drywall are getting underway.

USC’s first home game is scheduled for September 1, but the Rams kick off their season this Saturday. Renovations will continue through the season with a projected completion date of fall 2019.

We’re proud to work with Hunt Construction to preserve this celebrated landmark’s historical integrity while delivering vital improvements to enhance the fan experience.